George can do 3/5 of work in 9days.He then calls in pauls and they completed the work in 4days.How long paul would take long to complete the work?
a)32
b)28
c)35
d)30
Read Solution (Total 7)
-
- George work is (5/3)*9 =15;
1 day work of george is 1/15 ;
remaining is 2/5th;
paul & george work is 5/2*4=10 ;
their 1 day work is 1/10;
and only paul work is (1/10)-(1/15)=30
answer: 30 - 10 years agoHelpfull: Yes(32) No(1)
- one day work of george=(3/5)/9=1/15
1 day work of george+pauls= (2/5)/4=1/10
1 day work of paul=(1/10)-(1/15)=1/30
so pauls takes 30 days to complete the work. - 10 years agoHelpfull: Yes(6) No(0)
- remaining work 2/5
to be completed in 4 days
george in 9 days - 3/5 part of work
george in 1 days - (3/5)*(1/9)=1/15
in 4 days -4/15 part work
so paul has to do 2/5-4/15 part work in 4days
=2/15 part work 4 days
1 part work in 30 days - 9 years agoHelpfull: Yes(2) No(0)
- 30 days....
work done by George in 1day will be 1/15.
so it can be easily computed from that...
paul would take 30 days o complete the work - 10 years agoHelpfull: Yes(0) No(9)
- Paul will do work in xy/x-y days
15*10/5=30days - 10 years agoHelpfull: Yes(0) No(0)
- 5/3*9=15
5/2*4=10
1/10-1/15=1/30
no of days=30 - 9 years agoHelpfull: Yes(0) No(0)
- G -> 3/5 -> 9 -> 15 -> 6.66%
Remaining work is = 1-3/5=2/5
G+P -> 2/5 -> 4 -> 10 -> 10%
So, 10% - 6.66% = 3.34%
100/3.34 = 29.94
So the answer is : 30 days. - 9 years agoHelpfull: Yes(0) No(0)