a certain job was assigned to a group of men to do in 20days.but 12men did not turn up for the job and remaining people did the job in 32days.what is the original no. of members in the group?

Read Solution (Total 11)

TCS Other Question

A,B,C are three book printing machines. A takes 8 mins, B takes 12mins and C takes 10mins to print a book. if they work each day for 12 hours.what is the no. of books they print on each day? if 20 men or 24 women or 40 boys can do a job in 12days working for 8 hours a day.how many men working with 6 women and 2 boys take to do a job four times as big working 5 hours a day for 12days?