A,B and C can do a piece of work alone in 15 , 25 and 40 days respectively.They start together but B left the work as soon as the work was half completed and c left the work when it was 3/4th completed. A doing the remaining work alone. In how many days the work completed?
Read Solution (Total 9)
-
- ans 300/79+30/11+15/4=10.2747 days
- 12 years agoHelpfull: Yes(30) No(3)
- ans will be 10.2742 days
- 12 years agoHelpfull: Yes(7) No(1)
- 9.85 days...say nearly 10 days...madhavi...is it correct ???
- 12 years agoHelpfull: Yes(4) No(7)
- 8.5486 say 8.55 days.
total days = 300/79+30/11 + 15/4= 8.5486 days - 12 years agoHelpfull: Yes(2) No(7)
- its coming out to be 9.49 i.e. on 10th day work will be completed.
- 12 years agoHelpfull: Yes(2) No(10)
- 10.27 is correct answer................
- 12 years agoHelpfull: Yes(2) No(0)
- pls explain the method... how it is solved?
- 12 years agoHelpfull: Yes(1) No(0)
- plz mail me tcs new pattern paper akritigupta.2009@gmail.com
- 12 years agoHelpfull: Yes(0) No(3)
- ans:9.57 days
Take the L.C.M of 15,25,40 i.e 600 (assume this as total quantity of work to be done)
A completes 600/15= 40 units/day
B -> 600/25 =24
C-> 600/40=15
A+B+C together completes 79 units of work per day
Now, 300/79+( 150/(15+40))+150/40 =9.75 days approximately - 11 years agoHelpfull: Yes(0) No(0)