Bank Exam
Government Jobs Exams
Numerical Ability
Algebra
60 men complete work in 50 days. every 10 days 5 men left the work then how many days work will complete?
Read Solution (Total 2)
-
- 65 days
1 man's 1 day work=1/(60*50)=1/3000
Work completed by 60 men in first 10 days=10/50=1/5, so remaining work=4/5
For next 10 days 55 men will work, so work completed by them=55*10/3000=11/60
For next 10 days 50 men will work, so work completed by them=50*10/3000=10/60
For next 10 days 45 men will work, so work completed by them=45*10/300=9/60
.
.
Here we observe that, with decrease of 5 men after every 10 days, work completed is of the order 11/60, 10/60, 9/60, and so on , so we can sum these work completed to the remaining work=4/5 or 48/60
We have (11/60)+(10/60)+(9/60)+(8/60)+(7/60)+x/60=48/60
As 'x' here is equal to 3, so this is the duration where work is completed by 30 men=3/60=1/20
As 30 men's 1 day work=30/3000=1/100, so days required to complete the 1/20 of work=(1/20)/(1/100)=5
So total days required to completion of whole work=10 days (60 men)+10 days(55 men)+10 days(50 men)+10 days(45 men)+10 days(40 men)+10 days(35 men)+5 days(30 men)= 65 - 9 years agoHelpfull: Yes(0) No(0)
- since 60 man complete the work in 50 days
so 1 man can complete the work in 60*50=3000 days
w=worker, d= no. of days
w 9
60*10=600
55*10=550
50*10=500
45*10=450
40*10=400
35*10=350
30*5=150
total = 600+550+500+450+400+350+150=3000 ans
total - 9 years agoHelpfull: Yes(0) No(1)
Bank Exam Other Question