The time required for completing 3 tasks:type-1,type-2,type-3,by three carpenters is given in the table below.time specified in the table is for manufacturing single unit.
c1 c2 c3(c=carpenter)
type1 3 2 5
type2 6 5 4
type3 5 5 6
All the three carpenters start working simultaneously on one task each,with an objective to finish all the tasks as early as they can
1.C1 should work on:
A.Type1 B.Type2 c.Type3 D.none of the above
2.C3 should work on:
A.Type1 B.Type2 c.Type3 D.can't say
3.In how many hours can the entire work be finished?
A.4hr B.5Hr C.6hr D.7hr
4.In how many hours can 5 units of each type be prepared?
A.55hr B.25hr C.35hr D.10hr
5.If c2 is ristricted to prepare only Type-3 ,then c1 should work on:
A.Type1 B.Type2 c.Type3 D.can't say
Read Solution (Total 5)
-
- 1-c (As c2 takes less time in type 1 among all 3 so c2 work on type 1...Similarly,c3 on type 2 and c1 on type 3)
2-b
3-b (longest time taken by a carpenter is 5 that is by c1)
4-a (type1-2x5=10,type2-4x5=20,type3-5x5=25...so total time =10+20+25=55hr)
5-a (because c1 got less time in type 1 as compared to c3) - 8 years agoHelpfull: Yes(19) No(5)
- 4. As longest time for preparing single unit is 5hrs. so for 5units .. 5*5=25hrs.
answer is B. - 7 years agoHelpfull: Yes(2) No(0)
- i need answer for this
- 9 years agoHelpfull: Yes(0) No(1)
- please give the answers for this question
- 9 years agoHelpfull: Yes(0) No(0)
- 1-c
2-b
3-b
5-a - 9 years agoHelpfull: Yes(0) No(1)