sunil completes a work in 4 days,whereas dinesh completes the work in 6 days.ramesh 3/2 times as fast as sunil.the three together can complete the work the work in how many days?
Read Solution (Total 4)
-
- 6 sunil- 4
4 dinesh-6 24
9 ramesh- 4*2/3
so total days will be 24/(6+4+9) =24/19 ans - 7 years agoHelpfull: Yes(10) No(0)
- Time taken by Ramesh alone = (2/3) x 4 = 8/3 days
? Their 1 day's work = (1/4 + 1/6 + 3/8) = 19/24
So, together they can finish the work in 24 /19 days, i.e., 15/19 days. - 7 years agoHelpfull: Yes(1) No(4)
- 1 17/19 days
- 7 years agoHelpfull: Yes(0) No(0)
- Ans. 24/19
- 4 years agoHelpfull: Yes(0) No(0)