Time and Work
A and B can complete work together in 5 days. If A works at twice his speed and B at half of his speed, this work can be finished in 4 days. How many days would it take for A alone to complete the job?
Read Solution (Total 2)
-
- A one day work=1/x
B one day work=1/y
(A+B)=1/x+1/y=1/5
(x+y)/xy=1/5
5(x+y)=xy -------(1)
if A worked at twice =2/x
B worked at half=1/2y
2/x+1/2y=1/4
(4y+x)/2xy=1/4
8y+2x=xy-----(2)
substitute (2) in (1)
8y+2x=5x+5y
3y=3x
y=x that means number days worked by A alone is equal to B alone
substitute in (1)
1/x+1/x=1/5
2/x=1/5
A=10 days
B=10days - 5 years agoHelpfull: Yes(1) No(0)
- ans: 1
x+y=5
2x+.5y=4 or 4x+y=8
4x+y-x-y=8-5=3 or 3x=3
=> x=1 - 6 years agoHelpfull: Yes(0) No(2)