One person works for 8 days and take holyday of 9 days. If he starts work from Monday.in which days his 12th holiday?
Read Solution (Total 8)
-
- Sunday
(Mon to Mon=8 day)working day
(Tue to Thu=9 day)holiday
(Thu to Thu=8 day)working day
now Fri=10,sat=11,sun=12th holiday
- 11 years agoHelpfull: Yes(32) No(4)
- Ans. s mon...
m to m=8
tue to thu =9
fr to fr=8
sat,sund,mon - 11 years agoHelpfull: Yes(5) No(3)
- @NISHANT tue to wed=9 days
NOT tue to thu - 11 years agoHelpfull: Yes(3) No(0)
- ans is sunday
- 11 years agoHelpfull: Yes(1) No(2)
- 8:9
16+9=25,,25%7=4
from monday 4th day is friday
12th holiday is three days after that friday then ANS is:Monday - 11 years agoHelpfull: Yes(1) No(3)
- monday is the answer........
- 11 years agoHelpfull: Yes(0) No(2)
- working day starts with mon,therefore ,
mon=1 working day and sat is sixth working day,
after that
next week mon is 7th working day.
and tue is 8th working day
therefore,
wed is 1st holiday
thu is the 2nd holiday
fri is 3 rd holiday
sat is 4th holiday
mon is 5th holiday
tue is 6th holiday
wed is 7th holiday
thu is 8th holiday
fri is 9th holiday
similarly,
sat is to mon is again working days.
tue is 10th holiday
wed is 11th holiday
and
thu is 12th holiday.
therefore,
12th holiday is thursday. - 7 years agoHelpfull: Yes(0) No(0)
- An = a + (n-1)d
An = 9 +(12-1)8
An = 97
97/7 , remainder = 6 , after monday + 6 =SUNDAY - 6 years agoHelpfull: Yes(0) No(0)