1. Sixteen men complete a work in 24 days while 48 children can do it in 16 days. Twelve men

started the work, after 14 days 12 children joined them. In how Many days will all of them together

complete the remaining work?

Read Solution (Total 7)

Wipro Other Question

Ram ordered for 6 black toys And some additional brown toys. The price of black toy is 2.5 times that of a brown toy. While preparing the bill, the clerk interchanged the number of black toys and brown toys which increased the bill by 45%. Find the number of brown toys. Group discussion:privitazation in india