Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did, the work would have been completed in 3 days. To, complete the job alone, A would require how many days?

Read Solution (Total 3)

SSC Other Question

Three persons undertake to complete a piece of work for Rs.1200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get? A can do a piece of work in 20days and B in 30 days. They worked together for 7 days and then both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work?