P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?

Options
1) 8/15
2) 7/15
3) 11/15
4) 2/11

Read Solution (Total 1)

SSC Other Question

P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?

Options
1) 10 days
2) 14 days
3) 15 days
4) 9 days