Machine P can print one lack books in 8 hours. Machine Q can print the same number of
books in 10 hours while machine R can print the same in 12 hours. All the machines started
printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete
work. Approximately at what time will the printing of one lack books be completed?
A. 3 pm
B. 2 pm
C. 1:00 pm
D. 11am
Read Solution (Total 5)
-
- (P + Q + R)'s 1 hour's work =(1/8 + 1/10 + 1/12)= 37/120
Work done by P, Q and R in 2 hours=(2*37/120)= 37/60
Remaining work = (1- 37/60) = 23/60
(Q + R)'s 1 hour's work =(1/10 + 1/12)=11/60
so now, 11/60 work is done by Q and R in 1 hour
so 23/60 work will be done by Q and R in(60/11*23/60)= 23/11 hours = approx 2hrs
so, the work will be finished approximately 2 hours after 11 A.M.
i.e., around 1:00 pm - 10 years agoHelpfull: Yes(22) No(0)
- efficiency of P= 1/8
efficiency of Q= 1/10
efficiency of R= 1/12
P works for 2 hours and let time taken Q and R be x
so we can write
2(1/8)+x(1/10)+x(1/12)= 1 (total work done)
now solve for x
ans(approx)= 1:00pm
- 10 years agoHelpfull: Yes(2) No(0)
- ans is 1 .09 pm . and approximately its 1:00 pm.
- 10 years agoHelpfull: Yes(2) No(0)
- P can print 1 lack books in 8 hours
so it can print 25,000 books in 2 hours
Q can print 10,000 books in 1 hour
R can print 8333 books in 1 hour
so after 2 hours of work = 25000+20000+16666= 61666
so books remain 38334
so together they can print 18333 books in 1 hour
so in 2 hours they will print 36666 books.
and in the next hour they will complete the work.
11AM + 2 hours + 1 hour = 2 PM
B is the correct answer. - 10 years agoHelpfull: Yes(0) No(5)
- At 1.00pm work will be completed
- 10 years agoHelpfull: Yes(0) No(0)