TCS
Company
Numerical Ability
Time and Work
A can complete a project in 20 days while B can complete same project in 30 days. If A and B start working together and A leaves the work 10 days before completion of project, then in how many days the project will be completed?
Read Solution (Total 32)
-
- A's 1day work=1/20;
B's 1day work=1/30;
(A+B) 1day work=(1/20+1/30)=1/12;
It is given that A leaves the work 10 days before completion of the project..
Thus,B alone does the remaining job in 10 days.
So,In 10 days ,B can do 1/3 w ..
Thus,(A+B) have worked (1-1/3)=2/3 w..
(A+B)can do 1/12 work in 1 day...
They did 2/3 w in 8 days.
Total days=(8+10) = 18 (Ans)
- 10 years agoHelpfull: Yes(75) No(14)
- A's 1 day work=1/20
B's 1 day work=1/30
A+B's 1 day work= 1/20+1/30 = 1/12
so they ll complete d work in 12 days... but A left before 10 days... So both worked together only for days...
A+b's 2 day work= 2*1/12= 1/6
Remaining work=5/6
Remaining work can be done by B in 5/6*30= 25 days
So the project ll be completed in 2+25 = 27 days - 10 years agoHelpfull: Yes(54) No(48)
- A's 1 day work->1/20
B's 1 day work->1/30
let the project be completed in x days
for (x-10) days A & B work together
so,(1/20+1/30)(x-10)=y
wer,y->work completed in x-10 days
for 10 days B works alone if z is the work done by B
z=10(1/30)=1/3
total work=y+z
1=y+1/3
y=2/3
(1/20+1/30)(x-10)=2/3
so,x=18 days is the ans - 10 years agoHelpfull: Yes(15) No(0)
- Let's after 10 days B alone takes x days to complete a whole project.
then A's working day = x-10. and
A's 1 days Work = 1/10, B's 1 days Work = 1/30
therefore
A's (x-10) days work + B's x days work = 1 work
so (x-10)/20 + x/30 = 1 work
=> 30x-300+20x=600
50x=900
x = 18 days to complete whole work............. - 10 years agoHelpfull: Yes(12) No(3)
- 27 is wrong.
x-10/20 + x/30 =1
then x=18 is correct. - 10 years agoHelpfull: Yes(10) No(1)
- ans 27days
Together they can complete the work in
(20*30)/(20+30)=12days
A work for 2 days (12-10 days) and B work for x days
2/20+x/30=1
x=27
- 10 years agoHelpfull: Yes(6) No(15)
- A completes the work in 20 days
B completes the work in 30 days
L.C.M of 20 and 30 is 60, hence the total work to be done is 60 units
A's efficiency = 60/20 = 3 units/day
B's efficiency = 60/30 = 2 units/day
Given A left the project before 10 days , that means B has done the project alone in the last 10 days i.e, 10*( 2 units/day ) = 20 units.
Remaining work = 60 - 20 = 40 units
They both completed 40units of work
40units /(3+ 2)units/day=8
Therefore the project is completed in 10+8 = 18 days - 10 years agoHelpfull: Yes(6) No(2)
- a can complete in 20 days.
b " " " 30 days.
a+b = 1/20 + 1/30
=1/12
they can finish the work in 12 days.
but a leaves before 10 days.
b worked for 10 days i.e. 1/3 of the work was completed by b.
so they finished (1-1/3) i.e. 2/3 of the work.
so it took 12 x 2/3 = 8 days.
total time = 10+8 =18 days - 10 years agoHelpfull: Yes(5) No(2)
- Ans : 27 days
A one day work is =1/20
b one day works is=1/30
A+B works is =1/20+1/30=>50/600==>1/12
A+B can complete the work in 12 days..
A leaves the work 10 days before
12-10=2--->2*1/12=1/6
Remaining work is 1-1/6=5/6
B complete the project in 30 days=30*5/6=25days
Already they works 2 days so =25+2=27days
B complete the project in 27 days.......
- 10 years agoHelpfull: Yes(5) No(6)
- ans is 18
27 is the wrong answer . - 10 years agoHelpfull: Yes(4) No(1)
- x/20+x/30=1
(30(x-10)+20x)/600=1
50x=900
x=18.
answer is 18 days - 10 years agoHelpfull: Yes(2) No(1)
- A's 1day work=1/20;
B's 1day work=1/30;
let they finish their work in x days so
x(1/20 + 1/30) - 10(1/20)=1
-> x=18 days - 10 years agoHelpfull: Yes(1) No(1)
- The rate of A frac{1}{20} job per day;
The rate of B frac{1}{30} job per day.
Say they need t days to complete the project.
According to the stem we have that B works for all t days and A works only for t-10 days, thus frac{1}{20}*(t-10)+frac{1}{30}*t=1 --> t=18days.
Answer: A. - 10 years agoHelpfull: Yes(1) No(0)
- Let tank filled in x hour then
(x-10)/20+x/30=1
x=18
So project will complete in 18 days - 10 years agoHelpfull: Yes(1) No(0)
- formula for this type of questions is
D= b(n+a)/ (a+b)
b = no of days taken by B to finish the work
a =no of days taken by A to finish the work
n = days before A has left the work
substituting the values we will get
D= 18 days
further queries check website
http://a4academics.com/careers-guidance-jobs/68-quantitative-aptitude/674-time-and-work-shortcuts - 9 years agoHelpfull: Yes(1) No(0)
- Ans i....after 5days project will be complete
One day work of A is= 1/20
One day work of B is = 1/30
Work complete in 10 days by A = 1/2
Work complete in 10 days by B=1/3
Remaining work is =1-1/2-1/3=1/6
Time taken by B is =1/6*30=5
Ans is 5Days - 10 years agoHelpfull: Yes(0) No(14)
- (x-10)/20 +x/30=1
x=18 ans - 10 years agoHelpfull: Yes(0) No(0)
- 27 is the answer
- 10 years agoHelpfull: Yes(0) No(4)
- admin galat ans ko solved likha betha hain
- 10 years agoHelpfull: Yes(0) No(0)
- b filled 1/16th of tank in 3hrs
i.e
40
=>1/16th=40
=>full=640
therefor 10,20,40,80,160,320,640
tank can fill in 7hrs - 10 years agoHelpfull: Yes(0) No(0)
- its 18 days
- 10 years agoHelpfull: Yes(0) No(0)
- let total days be t.
-> t/20 + t-10/30 =1
->3t+2t-20 /60 =1
->t = 80/5
->t=16 days - 10 years agoHelpfull: Yes(0) No(0)
- (x-10)/20 + x/30 =1
x=18 ANS - 10 years agoHelpfull: Yes(0) No(0)
- 10 days only B works , so work by B in 10days=10*(1/30)=1/3
rest work=1-1/3=2/3
together work to complete 2/3 work
so (2/3)*((20*30)/50)=8
so 10+8=18 days
- 9 years agoHelpfull: Yes(0) No(0)
- Their 1 day work=(1/20+1/30)=1/12
10 days work = 10/12=5/6 so remaining work is 1/6
it will be done by B alone in 1/6*30 days=5 days
so total days to complete the project will be 10+5 =15 - 9 years agoHelpfull: Yes(0) No(0)
- 10 days working of A&B is =10(1/10+1/30)
= 2/5
remaining work=1-2/5
=3/5
B alone complete the work is=(3/5)*30
=18days - 9 years agoHelpfull: Yes(0) No(0)
- ans is 15
- 9 years agoHelpfull: Yes(0) No(1)
- x-10/20 + x/30 =1
x = 18 - 9 years agoHelpfull: Yes(0) No(0)
- The rate of A 120 job per day;
The rate of B 130 job per day.
Say they need t days to complete the project.
According to the stem we have that B works for all t days and A works only for tâ10 days, thus 120â(tâ10)+130ât=1 --> t=18days. - 9 years agoHelpfull: Yes(0) No(0)
- 18 is the answer
27 is wrong
- 9 years agoHelpfull: Yes(0) No(0)
- Answer is 18 days
- 6 years agoHelpfull: Yes(0) No(0)
- LCM of 20,30 = 60
A's 1 day work = 3
B's 1 day work = 2
A+B's 1 day work = 5
(A+B) * x days + B *10 days = 60
5*x + 2*10 = 60
5x = 40
x = 8
total days = 8+10 =18 - 6 years agoHelpfull: Yes(0) No(0)
TCS Other Question