GRE Exam Numerical Ability Time and Work

a small factory with 3 machines has a job of stamping out a number of pan covers, the newest machine can do it in 3 days, and the other machine can do it in 4days and the 3rd machine can do it in 6 days how many days will the factory take to do the job using the three machines