- Let W=total work done,M=work done by each men per day
K=work done by each kid per day
16*M*24=W
48*K*16=W
Let X be the remaining work done after 14 days
12*M*14+ [(12*M+12*K)*X] =W
putting M,K in terms of W in above equation, we get
X=12
So Remaining work done in 12 days
Total work done in (12+14)=26 days
- 10 years agoHelpfull: Yes(3) No(0)
- 16 men complete 1 work in 24 days , so 12 men complete work in 32 days
Similarly 48 kids compl work in 16 days , so 12 can cmplt it in 64 days
12 men wrk for 14 days work done by them in 14 = 14/32 = 7/16
Rem wrk = 1-7/16 =9/16
12M + 12K together can complete 1 work in (64*32)/(64+32)=64/3 days
12 M + 12 K complete 1 work in 64/3 days
So 12M+12K complete 9/16 work in 64/3 * 9/16 = 12 days