IBM
Company
Numerical Ability
Time and Work
A takes twice as much time as B or thrice as much time to finish a piece of work. Working together, they can finish the work in 2 days, can do the work alone in
A. 4 days B. 6 days
C. 12 days D. 15 days
Read Solution (Total 5)
-
- Let A,B,C takes time x,x/2,x/3
Then work
1/x+2/x+3/x=1/2
6/x=1/2
x=12
A takes 12 hr.B takes 6 hr.C takes 4 hr.
- 11 years agoHelpfull: Yes(18) No(2)
- 12 days.
4 + 6 + 12 + 15 = 37/3 = 12,3 - 13 years agoHelpfull: Yes(3) No(10)
Suppose A, B and C take x, x and x days respectively to finish the work.
2 3
Then, 1 + 2 + 3 = 1
x x x 2
6 = 1
x 2
x = 12.
So, B takes (12/2) = 6 days to finish the wor- 12 years agoHelpfull: Yes(3) No(7)
- A takes max twice time=2/X,
B takes max time =3/X,
c will takes max time =1/X,
A,B,C both the together will takes time(2/X+3/X+1/X=2) (both the A,B,C finish work 2 days)
so ans:
(2/x+3/x+1/x)=2days
6/x=2days =>X=2*6=12days
- 8 years agoHelpfull: Yes(1) No(1)
- Actual question is here and answer also
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
A. 4 days
B. 6 days
C. 8 days
D. 12 days
Answer: Option B
- 8 years agoHelpfull: Yes(1) No(4)