A can do a piece of work in 9 days. B can do the same in 12 days. In how many days can the work be completed if A and B work together?
a) 5 1/9 days
b) 5 1/4 days
c) 5 1/3 days
d) 5 1/7 days
Read Solution (Total 2)
-
- A's one day work=1/9
B's one day work=1/12
Both's one day work=1/9+1/12
=7/36
so they will take 36/7 days
36/7=5 1/7 - 13 years agoHelpfull: Yes(0) No(0)
- d) 5 1/7 days
A's one day work =1/9
B's one day work=1/12
(A+B)'s one day work=1/9+1/12=7/36
time taken=36/7=5 1/7 days - 12 years agoHelpfull: Yes(0) No(0)