X can do ΒΌ of a work in 10 days, Y can do 40% of work in 40 days and Z can do 1/3 of work in 13 days. Who will complete the work first?
Read Solution (Total 1)
-
- In 1 day,X does 1/40 work. In 1 day Y does 1/100 work. In 1 day Z does 2/39 work. So ans is Z.