Wipro Company Numerical Ability Time and Work

A can do a piece of work in 20 days and B in 30 days. A starts the work and worked for 6 days. Then B completed the remaining part of the work. In how many days was the work completed?

Read Solution (Total 2)

Wipro Other Question

A can do a piece of work in 24 days and B in 48 days. B joins A after A had worked alone for 6 days.In how many more days would the work get completed? A,B and C can together earn $1,620 in 9 days. A and C can earn $600 in 5 days where as B and C in 7 days can earn $910. Find the daily earnings of C?