Syntel Company Numerical Ability Time and Work

4 men and6 women can complete a work in 8 days, while 3 men and7 women can complete it in 10 days. In how many days will 10 women complete it?
1. 55 days
2. 40 days
3. 45 days
4. 60 days

Read Solution (Total 3)

Syntel Other Question

If 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is:
1. 2 : 1
2. 3 : 1
3. 3 : 2
4. 6 : 7
A and B complete a piece of work in 10 days.B and C in 12 days and C and A in 15 days.All the three of them started working and then B left after 4 days.C left 3 days after that and then immediately B joined A again to complete the remaining work.In how many days was the work
completed?
a)10 b)12 c)14 d)22