A can do a piece of work in 20 days, which B can do in 12 days. In 9 days B does ¾ of the work. How many days will A take to finish the remaining work?
Read Solution (Total 4)
-
- remaining work = 1-3/4 = 1/4
A can do full work in 20 days.
he wil do 1/4 th of work in 20*1/4= 5 days. - 12 years agoHelpfull: Yes(8) No(0)
- 5 days only.
1/4 of the work is left.
1/4*20 days+=5 days - 12 years agoHelpfull: Yes(1) No(0)
- 1-3/4 rem work
A 1 day work=1/20
so ans=20*(1/4)=5 days
- 12 years agoHelpfull: Yes(0) No(0)
- A is doing 10 days
- 6 years agoHelpfull: Yes(0) No(0)