TCS Company Numerical Ability Time and Work

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days 4/7 of the work is completed. How many additional men may be employed so
that the work may be completed in time, each man now working 9 hours a day?