5 skilled workers can build a wall in 20days; 8
semi-skilled workers can build a wall in 25 days; 10
unskilled workers can build a wall in 30days. If a te
am has 2 skilled, 6 semi-skilled and 5 unskilled
workers, how long will it take to build the wall?
Read Solution (Total 7)
-
- Ans : 15days
For Skilled
5 workers --------20 days
5 workers 1 day work= 1/20
1 worker's 1 day work= 1/(5*20)
Similarly,
For Semi-Skilled------
1 worker's 1 day work= 1/(8*25)
For Unskilled------
1 worker's 1 day work= 1/(10*30)
For 2 skilled,6 semi-skilled and 5 unskilled
workers
One day work= 2*[1/(5*20)] +6*[1/(8*25)] + 5*[ 1/(10*30)] = 1/15
Therefore no. of days taken= 15 - 9 years agoHelpfull: Yes(32) No(0)
- 2/100+6/200+5/300=40/600
so 600/40=15
so 15 days is the ans. - 9 years agoHelpfull: Yes(3) No(0)
- 5skill working for 20 days,8semi for 25 days and 10 unskilled for 30 days
5S×20=8SS×25=10US×30
It gives us
1S=2SS=3US
TAKE LCM HERE
LCM IS 6
S=6 Unit
SS=3Unit
US=2Unit
Now find Total work
Put any one of value ti get TW
5S×20=5×6×20=600
Now we have Find 2S+6SS+5US working together
12+18+10=40 unit 1 day
TW=600
600/40=15 Days
Guys it looks length for explaination but if u try to solve in this way u will get ans for sure within 10 sec if u practice the way I solved above problem
No need to take Pen and Paper..
All the best - 6 years agoHelpfull: Yes(2) No(0)
- 12men.............(18-6)12days
16men...............?
m1d1=m2d2
12*12=16*?
hence.?=9days - 8 years agoHelpfull: Yes(0) No(0)
- LCM METHOD
LCM OF 20,25,30=600unit(total work)
5 20day 600/20=30unit/day
8 25day 600/25=24unit/day
10 30day 600/30=20unit/day
5workers can work 30unit/day ..then 1 worker will do the work 30/5=6unit/day work done by 2 work=2*6=12
8workers can work 24unit/day ..then 1 worker will do the work 24/8=3unit/day work done by 6 workers=6*3=18
10 workers can work 20unit/day ..then 1 worker will do the work 30/10=3unit/day work done by 5 workers=2*6=12
12+18+15=54totoal work done by 2 S,6 SEMIS,5 UN
600/54=11.1 ANS=11
- 8 years agoHelpfull: Yes(0) No(0)
- 15
5 skilled workers can build a wall in 20 days
1 skilled worker can build the same wall in 100 days
Capacity of each skilled worker is 1/100
8 semi-skilled workers can build a wall in 25 days
1 semi-skilled worker can build the same wall in 200 days
Capacity of each semi-skilled worker is 1/200
Capacity of 1 unskilled worker is 1/300
Capacity of 2 skilled + 6 semi-skilled + 5 unskilled workers is 2(1/100) + 6(1/200) + 5/300
= 1/15 - 6 years agoHelpfull: Yes(0) No(0)
- ANS 15
LCM of 100,200 and 300 is 600 then (12+18+10=40)
600/40=15 - 6 years agoHelpfull: Yes(0) No(0)