40 men can complete a work in 40 days.they started the work together but at the end of each 10th day ,5 men left the job.the work would have been completed in how many days?
Read Solution (Total 3)
-
- Total men days = 40 *40 = 1600 men-days.
40 men work for 10 days = 400 men days
35men work for 10 days = 350 men days
30 men work for 10 days = 300 men days.
25 men work for 10 days = 250 men days
20 men work for 10 men days = 200 men days.
Total men days till now = 400 +350 +300 +250 +200 = 1500 men days.
Rest men days = 1600 - 1500 = 100 men days.
Now 15 men will work for complete 100 men days in = 100/15 = 6.66 days.
So total days = 10*5 + 6.66 = 56.66 days. - 7 years agoHelpfull: Yes(5) No(0)
- 55 days 40×40 =1600mendays
40×10=400. Men days left 1200 ... countiuy this and we will get answrr - 7 years agoHelpfull: Yes(2) No(0)
- the work will be completed in 240/7+10 days means 310/7 days
- 7 years agoHelpfull: Yes(0) No(0)