L&T Company Numerical Ability Time and Work

6 men and 10 boys finish a piece of work in 4 days, 5 men and 6 boys do it in 6
days. The ratio between the efficiencies of a man and boy is?

Read Solution (Total 2)

L&T Other Question

A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start
the work together but C leaves 4 days before the completion of the work. In how
many days is the work done?
A student is to answer 9 out of 12 questions in an examination such that he must choose at least 5 from the first six questions. The number of choices available to him is