6 men and 10 boys finish a piece of work in 4 days, 5 men and 6 boys do it in 6
days. The ratio between the efficiencies of a man and boy is?
Read Solution (Total 2)
-
- 6m+10m=1/4 ......(1)
5m+6b=1/6 ......(2)
solve 1 & 2,
m:b=3:2 - 6 years agoHelpfull: Yes(0) No(1)
- 6m+10b=1/4=>24m+40b=1
5m+6b=1/6=>30m+36b=1
Now Two Equations are Equal equate them:
24m+40b=30m+36b
6m=4b
m:b=2:3 - 5 years agoHelpfull: Yes(0) No(0)