Accenture Company Numerical Ability Time and Work

A, B and C can do a work in 5 days, 10 days and 15 days respectively. They started together to do the work but after 2 days A and B left. C did the remaining work (in days)
A. 1 B. 3 C. 5 D. 4

Read Solution (Total 7)

Accenture Other Question

Two trains, 200 and 160 meters long take a minute to cross each other while traveling in the same direction and take only 10 seconds when they cross in opposite directions. What are the speeds at which the trains are traveling?
A. 21 m/s; 15 m/s
B. 30 m/s; 24 m/s
C. 18 m/s; 27 m/s
D. 15 m/s; 24 m/s
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
A. 18 days B. 27 days C. 26.67 days D. 16 days