TCS
Company
Numerical Ability
Time and Work
A alone can do a piece of work in 10 days,B alone in 12 days,C alone in 15 days.If All start work at same day.A works for two days and C leaves before 3 days of remaining work.In how many days work will finish?
Read Solution (Total 29)
-
- B will work for all x days to complete the entire work
2/10+x/12+(x-3)/15=1
=>x=20/3 - 10 years agoHelpfull: Yes(62) No(9)
- LCM(10,12,15)=60
Let total work required to be done=60
A 1day work=6
B 1 day work=5
C 1 day work=4
Let the whole work is completed in x days
=>6(2)+4(x-3)+5x=60
x=20/3
- 10 years agoHelpfull: Yes(27) No(5)
- A's work done =1/10
B's work done =1/12
C's work done =1/15 in 1 days
A+B+C=1/10+1/12+1/15= 1/4
A,B,C work for 2 days so 2*1/4=1/2
C leaves before 3 days remaining work so 3*1/15=1/5
So total work done in 5 days(3+2)=1/2+1/5=7/10
remaining work = 1-7/10=3/10
3/10 work done by B and C in x days
3/10=x(1/12+1/15)
x=2 days
So A,B,C work for 2 days
B,C WORKS for 2 days
C works for 3 days
total 2+3+2=7 Ans
- 10 years agoHelpfull: Yes(23) No(14)
- 1 day work of a,b&c=(1/10+1/12+1/15)= 1/4
2 day work of a,b&c= 2*(1/4)= 1/2
left work 1-1/2= 1/2
3 day work of b= 3*1/12= 1/4
b& c together do 1/4th work in 5/3 days
total days =2+5/3+3= 20/3 - 10 years agoHelpfull: Yes(14) No(1)
- 7 days
total work 60
all work for 2 day ,work 30 done
c work for 3 days alone ,work 12done
remaining work to be done is 18,
18/9=2 days
so 2+2+3=7 is the ans
- 10 years agoHelpfull: Yes(7) No(4)
- take the lcm of all three numbers as number of units of work in this case 60
so A can do 6 units of work in 1 day
and B can do 5 units of work in 1 day
and C can do 4 units of work in 1 day.
Let work is completed in x days
A worked for 2 days so he completes 12 units of work
remaining is 45 units of work
As per problem B worked for (x-3) days so B completes (x-3)5 units of work
and C completes 4x units of work
so solve (x-3)5+4x=48
ans is 7 days
- 10 years agoHelpfull: Yes(3) No(0)
- 7 days , since a,b,c work together for 2 days , then work done =60 , reamining work 60 , c leaves before 3 days , hence work done by c=3*8=24 , remaining work is 36 which is completed in 2 days by b and c combined , hence total days =7
- 10 years agoHelpfull: Yes(2) No(3)
- A can do 1/10
b 1/12
c 1/15
A,B,c to gether 1/10+1/12+1/15=1/4
to gether 4
A works 2 days nd c leaves bfore 3 days so 4+3=7 - 10 years agoHelpfull: Yes(2) No(4)
- let a work efficiency as 1/5
b s work x/12
c 's (X-3)/15
by adding all, ans is : 20/3 - 10 years agoHelpfull: Yes(2) No(1)
- A does 10%
B 8.33%
C 6.66% work per day
together in two days they do 50% work
now 3 days before finish C leaves means B work alone for 3 days
3*8.33=25% work
left work is 25% that is being done by B and C
in 25/(8.33+6.66) =5/3 days
so total days=
2+5/3+3
20/3
- 10 years agoHelpfull: Yes(2) No(0)
- Answer=20/3
In 1 day work of A=1/10
In 1 day work of B=1/12
In 1 day work of C=1/15
Let x is working day of B and C
So,
2(A+B+C) + 3(B) + x(B+C)=1(=Total work)
2(1/10+1/12+1/15) + x(1/12+1/15) + 3(1/12)=1
x=5/3
Total working day=2+3+5/3
=20/3 - 10 years agoHelpfull: Yes(2) No(1)
- 2/10+(x-3)/12+x/15=1
x=7
- 10 years agoHelpfull: Yes(1) No(5)
- A-10days,b-12days,c-15days
let x be total no of days,then equationsare
x/12+(x-3)/15+2/10=20/3=6.667days - 10 years agoHelpfull: Yes(1) No(0)
- work completed by A,B,and C together is (1/10+1/12+1/15)=1/4
As A works for two days so work done by A is ((1/10)*2)=1/5
As C leaves before 3 days of remaining work ,so work will be done by B which is ((1/12)*3)=1/4
Now works remain to do (1-(1/5+1/4))=11/20
Now work done by B and C together in one day is (1/12+1/15)=9/60
so 9/60 work is done in one days
so 1 work will done in 60/9 days
and 11/20 work will be done in 60/9*11/20
so work will be finish in 11/3 +2+3=26/3 days
- 10 years agoHelpfull: Yes(1) No(0)
- let n is the total number of days, then work done by c is (n-3)/15.
work done by A is 1/5. work done by B is n/12.
(1/5)+(n/12)+((n-3)/15)=1
on solving n=20/3=6.6666666
i.e approximately 7 days of work. - 10 years agoHelpfull: Yes(1) No(0)
- A=1/10 B=1/12 C=1/15
1/10+1/12+1/15=1/4
TWO DAYS WORK: 2(1/4)=1/2
REMAINING WORK= 1-1/2=1/2
LET X=REMAINING DAYS
(X-3)(1/12)+(X/15)=1/2
X=5................ - 7 years agoHelpfull: Yes(1) No(0)
- 29/60 days
- 10 years agoHelpfull: Yes(0) No(5)
- total no days=7
- 10 years agoHelpfull: Yes(0) No(4)
- ans is 6(2/3) days
- 10 years agoHelpfull: Yes(0) No(1)
- Ans:6.2days
- 10 years agoHelpfull: Yes(0) No(0)
- 34/5 days
- 10 years agoHelpfull: Yes(0) No(0)
-
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is : - 10 years agoHelpfull: Yes(0) No(2)
- work is finished in 7 days
- 10 years agoHelpfull: Yes(0) No(7)
- 8.3 Days. As together a+b+c will complete it in 2d and b will complete it in 3 days so remaining work will be completed by (b+c) in 10/3 days. So total days required are 8.3 days.
- 10 years agoHelpfull: Yes(0) No(3)
- A 2 day work 2/10
let work is completed x day
2/10+x-3/12+x/15=1
x=7 - 10 years agoHelpfull: Yes(0) No(1)
- B will work for all x days to complete the entire work
2/10+x/12+(x-3)/15=1
=>x=20/3 - 10 years agoHelpfull: Yes(0) No(0)
- 60/9 final answer
- 10 years agoHelpfull: Yes(0) No(0)
- 14 daysss
- 10 years agoHelpfull: Yes(0) No(1)
- The answer is 7 days
- 4 years agoHelpfull: Yes(0) No(0)
TCS Other Question