Find the day of the week on 16th july, 1776.
Read Solution (Total 4)
-
- Answer is : Tuesday
Explanation:
split the year 1775 + 16th july1776
1700 years has 5 odd days
75 years has 93 odd days(18leap+57nonleap years)
16th july 1776 31+29+31+30+31+30+16=198 odd days
total odd days= 5+93+198=296%7=2(remainder)
2->Tuesday. - 13 years agoHelpfull: Yes(10) No(8)
- year code=4
month code=6
date =16
last 2 digit of year=76
(last 2 digit of year)/4=76/4=19(only exact quotient)
hence sum=4+6+16+76+19=121/7=2(remainder)
2 is tuesday - 11 years agoHelpfull: Yes(7) No(3)
- #Gokul Krishnan Sir, How can we get month code and year code.????
- 10 years agoHelpfull: Yes(4) No(1)
- #GOKUL KRISHNA sir, how do you calculated the year code and moth code .
- 10 years agoHelpfull: Yes(0) No(0)