Wipro Company Numerical Ability Time and Work

12 men complete a work in 9 days. After they have worked for 6 days, 6 more men joined them. How many days will they take to complete the remaining work?
(a) 2 days (b) 3 days (c) 4 days (d) 5days

Read Solution (Total 2)

Wipro Other Question

Seven men can complete a work in 12 days. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men?
(A) 5 (B) 6 (C ) 7 (D) 8 (E) none
A man, a woman and a boy can complete a job in 3,4 and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in ΒΌ of a day?
(a). 1 (b). 4 (c). 19 (d). 41