A contractor undertakes to complete a road 420 m long in 140 days and employ men for the work. After 70 days he finds that only 140 m of the road is made. How many men should the contractor employ more so that the work may be completed in time?
Read Solution (Total 2)
-
- wrong question..right q is -> A contractor undertakes to complete a rod 420 m long in 140 days and employs 28 men for the work. After 70 days he finds that only 140 m of the road is made. How many men should the contractor employ more so that the work may be completed in time? ans: 28 men
- 10 years agoHelpfull: Yes(5) No(0)
- 5 times more than they employ