• Result
  • Today's Puzzle
    • Previous Puzzles
    • Prize & Rules
  • Discussion Board
    • Suggestion Board
    • Trending Articles
  • Maths Tricks
  • Placement Papers
    • Placement Questions
    • Interview Experience
    • Placed user Comment
    • Group Discussion
  • English APP
  • login
  • Result
  • Today's Puzzle
    • Previous Puzzles
    • Prize & Rules
  • Discussion Board
    • Suggestion Board
    • Trending Articles
  • Maths Tricks
  • Placement Papers
    • Placement Questions
    • Interview Experience
    • Placed user Comment
    • Group Discussion
  • Walkins
    • Corporate Job Exam
    • Government Job Exam
    • Entrance Exam
  • Training
    • Internship
  • Placement Questions
  • /
  • AIEEE
  • /
  • Numerical Ability
  • /
  • Profit and Loss

Frequently Asked AIEEE Numerical Ability - Profit and Loss Sample Question with Solutions

AIEEE Select Another Category Profit and Loss Select Another Topic

Exam

  • ACIO 119
  • AIEEE 334
  • AMCAT 2636
  • Assessment 108
  • Bank 22
  • CAT 988
  • CMAT 82
  • Cocubes 39
  • Elitmus 2952
  • Exam 39
  • Gate 846
  • GMAT 107
  • Gmate 29
  • GRE 469
  • IIT-JEE 471
  • ITC 28
  • Maths Olympiad 205
  • MBA 3481
  • MCA 32
  • Other 159
  • Others 25
  • R-SAT 111
  • Self 68

AIEEE Question Topics

    Category (36)

    General Ability (1)

  • General Knowledge (1)
  • HR Interview (2)

  • Interview (1)
  • Logical Reasoning (4)

  • Blood Relations (1)
  • Letter Arrangement (1)
  • Missing Character (1)
  • Numerical Ability (22)

  • Age Problem (1)
  • Algebra (1)
  • Arithmetic (1)
  • Averages (1)
  • Co-ordinate geometry (1)
  • Number System (1)
  • Permutation and Combination (2)
  • Probability (4)
  • Profit and Loss (1)
  • Time Distance and Speed (1)
  • Programming (2)

  • Basics (1)
Keep an EYE (0)
Solved Question (1) UnSolved Question (0)
Pages: 11
Advertisements

(#M40000314) AIEEE QUESTION Keep an EYE Keep an eye puzzle Keep an eye puzzle

A contract on a construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for first day, Rs. 250 for second day, Rs. 300 for third day and so on. If the contractor pays Rs 27750 as penalty, find the number of days for which the construction work is delayed.

Asked In AIEEE (2055 years ago)
Solved C.T.Narayanan Read Solution (2)
Is this Puzzle helpful?   (34)   (14) Submit Your Solution Profit and Loss
Keep an EYE (0)
Solved Question (1) UnSolved Question (0)
Pages: 11
  • Login
  • Register

Resend

Sponsored Links

Advertisements

Challenger of the Day

no image
Dimple
India
Punjab
Time: 00:01:33
Points
19

Maths Quotes

" MATHEMATICS IS GIVES THE CREATIVITY THAT HOW TO SOLVE ANY PROBLEM IN ANY FIELDS "

Ajay Singh

Medicine makes people ill, mathematics make them sad and theology makes them sinful.

Martin Luther

Placed User Comments

M4Math helped me a lot.

Vipul Chavan 5 years ago

Thanks m4 maths for helping to get placed in several companies.
I must recommend this website for placement preparations.

yash mittal 5 years ago

Now enjoy Offline Access of latest Question.

Get M4maths app to avail expert's solution and latest selected questions.

Download m4maths app now

  • 2533K+Registerd user
  • 1774K+Engineers
  • 759K+MBA Asprirant
  • 3K+Enginnering College
  • 250+Company Exam
  • 150K+Interview Questions
  • Site Links
  • Home
  • Result
  • Today's Puzzle
  • Discussion Board
  • Maths Tricks
  • Advertise with us
  • Contact Us
  • Useful Info
  • Maths Quotes
  • Previous Puzzles
  • Prize
  • Privacy Policy
  • Disclaimer and Copyright
  • Terms and Conditions
  • Sitemap
  • Placement papers
  • TCS Placement Paper
  • HCL Placement Paper
  • INFOSYS Placement Paper
  • IBM Placement Paper
  • SYNTEL Placement Paper
  • TECHNICAL Interview
  • HR Interview
All rights are reserved to @m4maths.com