Latest Postal assistant karnatak circle Aptitude Question SOLUTION: 36 me were employed to do a piece of work in 48 days.But it was found that in 24 days only 2/5th of the work is done.How many additional men are to be taken to finish the work in t
36 me were employed to do a piece of work in 48 days.But it was found that in 24 days only 2/5th of the work is done.How many additional men are to be taken to finish the work in time?