A rectangular plot of size 18*8 m^2 has to be digged upto 8 m. depth. Cost of work increases continuously
from top to bottom. It starts from 10 rupee per cubic meter at top to 60 rupee per cubic meter at bottom.
Cost of complete work is ?
Total volume of digged earth = 18*8*8 = 1152 m3
Average cost of work = (10 + 60)/2 = 35 rupee per cubic meter
Total cost of work = 1152 * 35 = 40320 rupee