John and Nick together can complete a work in 10 days. They plan to do the job in a different way. In first day John do it whereas Nick do it for the next 2 days and this pattern is repeated again and again. If they have to finish the work in 18 days, then in how many days the man who finish the work do this work alone.
Let John do it alone in x days and Nich alone in y days,
then according to first given condition
1/x + 1/y = 1/10 (1)
According to second condition
18/3 (1/x + 2/y) = 1
1/x + 2/y = 1/6 (2)
On solving (1) & (2) y = 15 & x = 30
So Nick will finish the work in 18 days & he complete it in 15 days
Option 3)