Rupendra forms a wall in 10 days and Shailendra forms it in 15 days. Rependra and Shailendra start the work of forming wall together but after 2 days Rupendra leaves the work. How many days are required for making the remaining wall by Shailendra?
One day work of Rupendra = 1/10
One day work of Shailendra = 1/15
One day work of R and S = 1/10 + 1/15
= 1/6
After 2 days of work remaining work = 1- (2*1/6) = 4/6
No. of days required by S for doing this work = (4/6) / (1/15)
= 10