Rohan and Suraj can do a piece of work in 12 days; Suraj and Mahesh in 15 days; Mahesh and Rohan in 20 days. In how many days will they finish it together.
(R+S)'s day's work = 1/12;
(S+M)'s 1 day's work = 1/15
(M+R)'s 1 days's work = 1/20
Adding : 2(R+S+M)'s 1 day's work = (1/12 + 1/15 + 1/20)
= 12/60 = 1/5
=> (R+S+M)'s 1 day's work = 1/10
So, they together can finish the work in 10 days.