P is able to do a piece of work in 15 days and Q can do the same work in 10 days. If they can work together for 2 days, what is the fraction of work left?
Amount of work P can do in 1 day = 1/15
Amount of work Q can do in 1 day = 1/10
Amount of work P and Q can do in 1 day = 1/15 + 1/10 = 5/30 = 1/6
Amount of work P and Q can together do in 2 days = 2 × (1/6) = 1/3
Fraction of work left = 1 – 1/3= 2/3